I was told by my salesman that I would be up and running in four weeks after installation. Panels were installed 10/28/2015. I am still not up and running after several calls to Trinity and personally expediting final inspections. After talking to Trinity today they claim they are awaiting an SRP# from the state for which they applied on line 11/11/2015. I personally called NJ Clean Energy Program -*******278) the program that issues the SRP# - and was informed that it takes aprox 4 months to be issued a SPR# and that Trinity was suppose to have had this number before installation. They said I will probably not be up and running until March if I am lucky. I would never refer Trinity and am calling the BBB.